Huge progress has been made on B2B this week where the RC wall, pictured above, is now advancing to its 6th floor level where structural steel and precast floor units will be visible next week.
Further developments on the 1st, 2nd, and 3rd floors of the Duplex apartments have resulted in the commencement of M&E installation.
This week also saw the RC works to the B4 stairs being completed with the roof structure due to be installed in the forthcoming weeks.