Building our Future Together

Category

News
The hoarding to New Wapping Street has been dropped in the past week. This has given members of the public their first sight of the new Central Bank Headquarters at street level. Works are fast progressing in this area to create the final streetscape that will become part of the broader public spaces in this...
Read More
Pictured above are ongoing works of the most recent 3rd pour to the 5th Floor of the new LinkedIn project. The project is located at Wilton place and 65% of the slab is scheduled be completed today with the remainder of the pour to be completed by the end of the week.  
Read More
Huge progress has been made on B2B this week where the RC wall, pictured above, is now advancing to its 6th floor level where structural steel and precast floor units will be visible next week. Further developments on the 1st, 2nd, and 3rd floors of the Duplex apartments have resulted in the commencement of M&E...
Read More
The last section of level 4 concrete pour saw its completion this week. This has resulted in the basement, ground, 1st, 2nd, 3rd and 4th floors all being completed. Level 5, pictured above, and the roof slab, are scheduled to be completed by early August. Other progress across the site included the commencement of the...
Read More
The commercial office fit-out and refurbishment works for Amazon has completed all its minor demolitions which include internal walls and ceilings. The project is currently in the process of installing new partitions, showers & bathrooms and will soon be beginning the installations of the new furniture arrangements. Winthrop were awarded the M&E contract and are currently making their...
Read More
Work continues on the B2B development as the apartment block is now fully enclosed in scaffolding up to the 5th floor level. Furthermore, a concrete pump is now set up in the compound and is currently pumping concrete to the 4th floor.  
Read More
External – The installation of the Solar Shading Veil has just commenced. Over the next few months this will be the biggest visible change as this new skin will wrap the entire building. The Atrium Glazing is now almost complete so passers by can see the Vertical Glazing on the south façade. Internally, the workers...
Read More
Our latest concrete pour commenced at 7.00am on Monday 30th of May. A licence from Dublin City Council was put in place for works after 6.00pm. Here you can see the progression of the current LinkedIn project.
Read More
The new daa Tasc project commenced in mid April 2016 and entails the refurbishment of a 6 storey office building for the new Multinational Client. Notable points at the early stages of this project include:  Floor space of 400msq per floor with a total 2000msq area.  Design Build project (BKD, OCSC, 2HQ and MJP) with finish date...
Read More
The design and build redevelopment of the HOB, former Aer Lingus head office at the airport, commenced in March 2015 and is scheduled for completion in February 2016. It is part of the first phase of a planned 70-acre business park aimed at international high-tech companies involved in research and development as well as other...
Read More