Skip to main content

A major milestone was reached this week on Dublin Landings, with the completion of the Podium Slab for Blocks DL3,4,5 & B.

 

Since the first concrete pour on the 7th June this year approximately 5000 tons of reinforcement and 21,000 cubic meters of structural concrete have been installed. This averages 36 tons of Reinforcement tied, and 155 cubic meters of concrete placed per day over the last 28weeks.

Onwards and upwards for next year