February has seen two major milestones on the project with the completion of the concrete frame and the removal of the first tower crane.

External windows are now substantially complete across all cores, with brickwork progressing on all 9 cores and roofing works progressing on 5 of 9 cores.

Internal fitout works continue to progress well with works now progressing in all 9 cores.