Works have continued to progress well into March, with roofing works now progressing across all cores.
Brickwork has now completed on Core D with snagging works commenced ahead of scaffold removal commencing in April.
Drainage and civil works have re-commenced along what will be a new road, namely Dargan Street.
Waterproofing works have also commenced on Block 6 podium ahead of landscape works commencing.
Internal fitout is continuing at pace in all cores, with apartment completions commencing shortly.