Block 6 works have progressed well during May with the ground floor walls progressing well in Core D and the ground floor slab poured in Core C. Substructure works continue to progress well in Core A, Core B and Core D, with main drainage works well advanced.

Block 5 has seen good progress with substructure works progressing well in Core 2 and Core 3 and now commencing in Core 4. Core 1 substructure works are substantially complete with works are under way on the ground floor slab.

May has also seen the addition of a 5th tower crane, with the final crane due for erection in June.