As the impressive new seven storey Central Bank of Ireland eco-headquarters nears completion elements of the project are being furnished. The cedar seating on the terrace is complete and the final landscaping elements in the terrace area such as the planter soil, shrubs and LED lighting will be completed in the coming days. The collaboration spaces either side of the Atrium are fully fitted and furnished and now ready for use.
The final bespoke ceiling fixtures and solid oak floor finishes are being fitted this week and the lifts are now operational with the leather panelling, stainless steel surrounds, and access control security call being installed and commissioned in the lift lobbies.
The Atrium area is also receiving its finishing touches and is being cleaned internally with help of a custom gantry crane that allows the cleaners to access the North, South, East and West of the Atrium as well as up and down between floors.