Block 6 concrete frame continues to progress well with Core D up to fourth floor level, Core C up to third floor, Core B up to first second floor and Core A up to first floor. Core E ground floor slab will be completed in early September. Façade works have also commenced with windows now being installed in Cores D & C and brickwork commenced in Core D.

Block 5 concrete frame is now also progressing, with Core 1 on second-third floor walls, Core 2 second floor slab has been poured and Core 3 ground-first floor walls substantially complete and preparations for the first floor podium transfer slab underway. Façade works have also commenced, with window installations in Core 1.