Skip to main content

Construction Update – July 2024

Works have progressed well over the past month. Our site hoarding is now largely complete and works are ongoing within the site boundary. Notices have been erected on the site hoarding with a QR code which will bring you directly to the project website where the most up to date information can be found with relevant updates on derogations and/or any other extenuating events.

The bulk excavation for phase 1 is now complete which will we see a reduction in traffic on this side of the project. Piling is ongoing and works will begin in preparation for the reinforced concrete works to commence over the coming weeks.

Bulk excavation works are progressing in Phase 2 and is targeting completion towards the end of August.