Phase 1 has now been successfully completed with the building now live on the DCC Building Control Register.

On Phase 2 external works are largely complete on the north and west elevations and we are currently working on the east and south. Works to internal courtyards are largely complete. Internal works are in the final snagging stages.

Please see below summary of upcoming works to be aware of. Please note as with all construction works these are subject to change and we endeavour to keep you updated as soon as we become aware.

Week Commencing 3rd August

 

Tar to Royal Canal Way Section of Road
Week Commencing 10th August

 

Tar to Rathborne Boulevard Phase 2 Side
Week Commencing 17th August

 

Nothing to note at present.
Week Commencing 24th August

 

Nothing to note at present.

Thank you for taking the time to read this newsletter. We are grateful for your patience and understanding and will continue to do our best to minimise disruptions.