On Phase 1 works are largely complete with snagging and final touches being put on various areas both internally and externally. We are currently awaiting a date from DCC to carry out a final walk ahead of the buildings being confirmed as ready for occupation.
On Phase 2 external works are now being progressed on all elevations as we work our way out of phase 1. Internal works are progressing in line with our programme and both design team and client snagging is progressing.
Please see below summary of upcoming works to be aware of. Please note as with all construction works these are subject to change and we endeavour to keep you updated as soon as we become aware.
| Week Commencing 22nd June |
| Nothing to note at present. |
| Week Commencing 29th June
|
| Section of landscaping to north of median area will be prepped for trees and express lawn seeds sown. We are currently awaiting date for trees as we are currently outside tree planting season.
Works at intersection of the Tallow and Rathborne Road. Traffic management will be put in place to facilitate works. |
| Week Commencing 6th July
|
| Nothing to note at present. |
| Week Commencing 13th July
|
| Nothing to note at present. |
| Week Commencing 20th July
|
| Nothing to note at present. |
| Week Commencing 27th July
|
| Nothing to note at present. |
Thank you for taking the time to read this newsletter. We are grateful for your patience and understanding and will continue to do our best to minimise disruptions.