Significant progress has been made on site during June and July.

Block 6 has seen 5 of 6 ground floor slabs completed and the concrete frame progressed well with Core D up to third floor level, Core C up to second floor and Core B up to first floor.

Block 5 has seen 3 of 4 ground floor slabs completed, with the concrete frame also commenced, with Core 1 almost up to second floor, and Core 2 up to first floor.

There has also been significant civils works completed with the majority of the main drainage and utility services complete.