On Phase 1 we are currently in the process of final testing and commissioning and snagging internally. Works externally are progressing well with most of the focus on the central area between phase 1 and 2.
On phase 2 external works are progressing within the courtyards and along the north. All brick and façade works are largely complete and scaffold is now being removed in all areas. Internal works are progressing in line with our programme.
The works along the canal greenway have been completed. We are targeting reopening of this next week.
Works in the central median are also largely complete and has been reopened to the public.
Please see below summary of upcoming works to be aware of. Please note as with all construction works these are subject to change and we endeavour to keep you updated as soon as we become aware.
| Week Commencing 25th May |
| Tower Crane 3 removal has been moved back to the 15th June.
We are aiming to get the Median reopened towards the end of this week. There will be some minor works to Rathborne Boulevard Phase 1 side resetting all the manhole lids and gullies to the new road level. |
| Week Commencing 1st June |
| Canal Works being offered to Waterways Ireland as complete. Looking to reopen as soon as possible. |
| Week Commencing 8th June |
| Nothing to note. |
| Week Commencing 15th June |
| Removal of Tower Crane 2 and 3 |
| Week Commencing 22nd June |
| Target for Tar of Rathborne Boulevard Phase 2 side. |
| Week Commencing 29th June |
| Nothing to note. |
Thank you for taking the time to read this newsletter. We are grateful for your patience and understanding and will continue to do our best to minimise disruptions.