Block 6 concrete frame is advancing well with Core D progressing from fifth-sixth floor, Core B progressing from fourth-fifth floor, Core B progressing from third-fourth floor, Core A progressing from second-third floor and Core E first floor slab completed and first-second floor walls commencing shortly.
Window installations are now progressing on Cores D, C, and B with brickwork commenced on Core D, C and B.
Internal fitout works have also commenced with first fix partitions and mechanical service installations in Core D.
Block 5 concrete frame is also advancing well, with Core 1 and Core 2 progressing from third-fourth floor, Core 3 second floor screed preparation works are underway and Core 4 ground-first floor walls are progressing.
Façade works have commenced with window installations on-going in Cores 1 and 2, and brickwork commencing on Core 1.