The last section of level 4 concrete pour saw its completion this week. This has resulted in the basement, ground, 1st, 2nd, 3rd and 4th floors all being completed. Level 5, pictured above, and the roof slab, are scheduled to be completed by early August.
Other progress across the site included the commencement of the M&E installation by Mercury Engineering and the first sightings of the external façade, with bracket installation progressing ahead of the first unitised panels which have been installed on the Lad Lane elevation