A single storey 1,960m2 office building on a 6 hectare site at the SAM Data Centre Campus in Farciennes, near Charleroi in Belgium.

The project consists of all the construction works required to construct and commission a 1,960m2 office building and the associated parking, landscaping and utility works. This Office at Data Centre (ODC) building will include a main entrance area, open plan desk space, meeting rooms, training rooms, a large catering kitchen, a micro kitchen and toilet facilities.

Externally, a 136 bay car park will be constructed including 22 EV charging points. The project is currently in preconstruction, with works commencing on site in September 2026 and a planned completion date of September 2027.

CLIENT

Confidential

ARCHITECT

Biermar and Biermar

STRUCTURAL ENGINEERS

Arcadis

DURATION

12 Months

QUANTITY SURVEYOR

Linesight

SERVICES ENGINEERS

Arcadis

LOCATION

Farciennes, Belgium

VALUE

€29M