Hovione Pharmaceutical

Fit-out of Building 10, a spray drying facility used by Hovione for the spray drying of multiple APIs.

The facility currently houses one spray drying equipment train, a PSD5 unit. Site spray drying capacity is being increased by the installation of a smaller spray drying train in the southeast corner of the existing facility.

The scope includes demolition and alteration works, formation of wall opes and floor penetrations, finishes, drainage, minor structural steelwork and firestopping, modifying the existing structure to allow installation of the PSD4 modules and associated process vessels and equipment. All works are completed on a live facility, sequenced and scheduled with Hovione and the project CMT.

CLIENT

Hovione Limited

ARCHITECT

DPS Engineering

STRUCTURAL ENGINEERS

DPS Engineering

DURATION

7 Months

QUANTITY SURVEYOR

Deasy Walley Partnership

SERVICES ENGINEERS

DPS Engineering

LOCATION

Ringaskiddy, Co. Cork

AREA

612m2