Welcome to the LDA Clongriffin Project
Welcome to the informative website for the LDA Clongriffin project.
The webpage is designed to provide local residents with information about the ongoing works being carried out at LDA Clongriffin.
We would recommend that you subscribe to this site using the below form provided to receive email and notifications of new notices / construction notices and information posts going forward with regards to this project.
Upcoming Events
Friday 30th October
Dear Residents
Please be advised Uisce Eireann are progressing well with their work around the site and the following closures are imminent
• Partial closure to Belltree Avenue with local access only – Works commence 30/10 for circa 7 days
• Full closure to Park Street with local access only via Dargan Street – Works commence approximately 11/11 for circa 6 days
We understand the inconvenience these works have/are causing however they are outside of our control. We are communicating timelines and dates to the best of our knowledge based on the information being provided
Signed
Walls Site Management
Friday 16th October
Dear Residents
Please be advised Uisce Eireann have commenced works in the vicinity of the site and partial road closures are now imminent
Please see below updated phasing as works are progressing faster than anticipated
• Partial closure to Park Street with local access only – Works commence 20/10 for circa 3 days
• Full closure to Park Street with local access only via Dargan Street – Works commence 23/10 for circa 4 days
• Partial closure to Belltree Avenue with local access only – Works commence 23/10 for circa 4 days
As we approach the end of our works, we would like to take this opportunity to thank you for your patience throughout the works and we appreciate your understanding with these upcoming works
Signed
Walls Site Management
Thursday 8th October
Dear Residents
Please be advised that Uisce Eireann will be completing essential works to Park Street and Belltree Avenue over the coming weeks, commencing provisionally week commencing October 26th
These works are not managed directly by Walls Construction or the LDA. These works are managed and being completed by Uisce Eireann due to requirement for essential upgrade works to systems. Works will be completed over 3 phases, taking 5 days per phase. The dates we have are provisional and will move based on actual start date and timelines for completions. Although we have no control over these works, we will work to give as much notice as we can and ensure areas are returned as soon as possible
Phasing will be undertaken as follows
• Partial closure to Park Street with local access only – Provisionally, week commencing 26/10
• Full closure to Park Street with local access only via Dargan Street – Provisionally, week commencing 02/11
• Full closure to Belltree Avenue with local access only – Provisionally, week commencing 09/11
As we approach the end of our works, we would like to take this opportunity to thank you for your patience throughout the works and we appreciate your understanding with these upcoming works
Signed
Walls Site Management
Thursday 17th September
Due to unforeseen circumstance the traffic management plan in place on Belltree Avenue and Park Street will be in place until close of business Tuesday 22nd September. We apologise for the inconvenience caused .
Friday 11th September
Due to essential works along Belltree Avenue and Park Street, below traffic management will be implemented from 7am Wednesday 16th September until 1pm Friday 18th September. We apologize for any inconvenience caused and thank you for your patience throughout the works.
Thursday 3rd September
Due to essential works along Belltree Avenue, below traffic management will be implemented from 6am Tuesday 8th September until 1pm Thursday 10th September. We apologize for any inconvenience caused and thank you for your patience throughout the works.
Monday 31st August
Please be advised we will be completing fire alarm commissioning for Block 5 on Tuesday 1st September which will involve fire alarm sounder activations and testing throughout the day.
Thursday 23rd July
Please be advised, we have been granted a derogation until 10pm on Friday 24th July and until 8pm on Saturday 25th July to facilitate the safe removal of Tower Crane 5. We thank you for your patience throughout our works.
Friday 17th July
Please be advised, we have been granted a derogation until 10pm on Friday 17th July and until 8pm on Saturday 18th July to facilitate the safe removal of Tower Crane 2. We thank you for your patience throughout our works.
Wednesday 8th July
Please be advised, we have been granted a derogation until 10pm on Friday 10th July and until 8pm on Saturday 11th July to facilitate the safe removal of Tower Crane 1. We thank you for your patience throughout our works.
Wednesday 17th June
Please be advised, that works to Park street will commence WC 22/06 and will take circa 4-6 weeks to complete. Works will be undertaken intermittently with traffic management and adequate supervision at all times. We thank you for your patience throughout our works.
Friday 17th April
Please be advised, that at Clongriffin there will be road closures, starting from 11th of May.
Please see traffic management plan in the April Construction Update.
Monday 16th February
Please be advised, that the removal of our Tower Crane 3 (TC3) will be commencing on Tuesday 17th February.
Friday 19th December
Please be advised, our site will close on Tuesday 23rd December and will re-open on Monday 5th January. During the holiday period, we will have a full-time security guard on site should any issues arise
Should you have any issues, please contact ldaclongriffin@walls.ie.
Wednesday 6th August
In order to facilitate crane erection works and concrete finishing, derogation has been granted by DCC for the 6th of August from 18:00 to 22:00 and for Friday the 8th of August from 18:00 to 23:00 to achieve the required finish.
We apologise for the inconvenience.
Tuesday 22nd July
In order to facilitate a concrete pour, a derogation has been granted by DCC on 23rd and 25th July. This derogation will allow for the completion of concrete works from 18:00 to 23:00 to achieve the required finish.
Wednesday 25th June
In order to facilitate a concrete pour, a derogation has been granted by DCC for Thursday 26th June. This derogation will allow for the completion of concrete works to continue until 23:00 to achieve the required finish.
Wednesday 18th June
In order to facilitate a concrete pour, a derogation has been granted by DCC for Friday 20th June. This derogation will allow for the completion of concrete works to continue until 23:00 to achieve the required finish.
Friday 6th June
In order to facilitate concrete pours next week, derogations have been requested from DCC for Monday 9th and Friday 13th June. These derogations will allow for the completion of concrete works to continue until 23:00 to achieve the required finish.
Monday 26th May
In order to finish a concrete pour in the Block 6 courtyard carpark, we have been granted a derogation from DCC for Wednesday 28th May to achieve the required finish. A small crew will be on site with localised task lighting only. We will endeavour to finish before 11pm.
Tuesday 20th May
In order to facilitate a concrete pour, we have been granted a derogation from DCC for Tuesday 20th May until 11.00pm to achieve the required concrete finish.
Wednesday 30th April
Block 5 & 6 Clongriffin – Concrete slab Works
The Block 5 and 6 project has now entered superstructure frame stage. Block 6, Core D, which is our foremost block in terms of program will now commence having its ground floor slab completed. This floors is an in-situ reinforced slab which requires a high level of finishing to achieve the required tolerances. Dublin City Council have granted permission for an extension of site working hours for these finishing works.
Planned dates & times for concrete slab finishing works are as follows:
• Friday 2nd May 18:00Hrs – 23:00Hrs
Monday 10th February
We would like to apologise for the inconvenience caused by site lighting and a generator on site running over the weekend, these issues are currently being resolved by our Site Manager.
Thursday 23rd January
Works are currently progressing well on site, and we will be commencing with piling works next week. Delivery of the piling rig and installation of piles is scheduled for Tuesday 28th January.
Thursday 23rd January
As a result of the national status red weather warning, our site will be closed on Friday 24th January. A site inspection will be carried out on Friday afternoon once the red warning has been lifted, and conditions are safe for our teams to travel to site.
News Updates
Want to stay up to date with all site related news? Sign up to our form below: