Welcome to the LDA Clongriffin Project

Welcome to the informative website for the LDA Clongriffin project.

The webpage is designed to provide local residents with information about the ongoing works being carried out at LDA Clongriffin.

We would recommend that you subscribe to this site using the below form provided to receive email and notifications of new notices / construction notices and information posts going forward with regards to this project.

Upcoming Events
Monday 16th February

Please be advised, that the removal of our Tower Crane 3 (TC3) will be commencing on Tuesday 17th February.

Friday 19th December

Please be advised, our site will close on Tuesday 23rd December and will re-open on Monday 5th January. During the holiday period, we will have a full-time security guard on site should any issues arise
Should you have any issues, please contact ldaclongriffin@walls.ie.

Wednesday 6th August

In order to facilitate crane erection works and concrete finishing, derogation has been granted by DCC for the 6th of August from 18:00 to 22:00 and for Friday the 8th of August from 18:00 to 23:00 to achieve the required finish.
We apologise for the inconvenience.

Tuesday 22nd July

In order to facilitate a concrete pour, a derogation has been granted by DCC on 23rd and 25th July. This derogation will allow for the completion of concrete works from 18:00 to 23:00 to achieve the required finish.

Wednesday 25th June

In order to facilitate a concrete pour, a derogation has been granted by DCC for Thursday 26th June. This derogation will allow for the completion of concrete works to continue until 23:00 to achieve the required finish.

Wednesday 18th June

In order to facilitate a concrete pour, a derogation has been granted by DCC for Friday 20th June. This derogation will allow for the completion of concrete works to continue until 23:00 to achieve the required finish.

Friday 6th June

In order to facilitate concrete pours next week, derogations have been requested from DCC for Monday 9th and Friday 13th June. These derogations will allow for the completion of concrete works to continue until 23:00 to achieve the required finish.

Monday 26th May

In order to finish a concrete pour in the Block 6 courtyard carpark, we have been granted a derogation from DCC for Wednesday 28th May to achieve the required finish. A small crew will be on site with localised task lighting only. We will endeavour to finish before 11pm.

Tuesday 20th May

In order to facilitate a concrete pour, we have been granted a derogation from DCC for Tuesday 20th May until 11.00pm to achieve the required concrete finish.

Wednesday 30th April

Block 5 & 6 Clongriffin – Concrete slab Works

The Block 5 and 6 project has now entered superstructure frame stage. Block 6, Core D, which is our foremost block in terms of program will now commence having its ground floor slab completed. This floors is an in-situ reinforced slab which requires a high level of finishing to achieve the required tolerances. Dublin City Council have granted permission for an extension of site working hours for these finishing works.
Planned dates & times for concrete slab finishing works are as follows:

• Friday 2nd May 18:00Hrs – 23:00Hrs

Monday 10th February

We would like to apologise for the inconvenience caused by site lighting and a generator on site running over the weekend, these issues are currently being resolved by our Site Manager.

Thursday 23rd January

Works are currently progressing well on site, and we will be commencing with piling works next week. Delivery of the piling rig and installation of piles is scheduled for Tuesday 28th January.

Thursday 23rd January

As a result of the national status red weather warning, our site will be closed on Friday 24th January. A site inspection will be carried out on Friday afternoon once the red warning has been lifted, and conditions are safe for our teams to travel to site.

News Updates
Want to stay up to date with all site related news? Sign up to our form below:

    For more information, please email:
    ldaclongriffin@walls.ie